ANSI EIA 364-107-2000 pdf download Eye Pattern and Jitter Test Procedure for Electrical Connectors, Sockets, Cable Assemblies or Interconnection Systems
1 Introduction
1.1 Scope
This procedure is applicable to electrical connectors, cable assemblies, or interconnection systems.
1.2 Object
This standard describes methods for measuring an eye pattern response and jitter in the time domain.
1.3 Definitions
1.3.1 Eye pattern
An oscilloscope display of synchronized pseudo-random digital data (signal amplitude versus time), showing the superposition of accumulated output waveforms.
1.3.2 Jitter
The difference between the earliest and latest times at which a signal crosses a specified reference voltage level.
1.3.3 Bit period
The time interval between the successive like edges (rise to rise or fall to fall) of the clock signal. This is the reciprocal of the clock frequency.
1.3.4 Skew
The difference in propagation delay between two signal paths.
1.3.5 Measurement system rise time.
Rise time measured with fixture in place, without the specimen, and with filtering (or normalization). Rise time is typically measured from 10% to 90% levels.
2 Test resources
2.1 Equipment
2.1.1 High speed pattern generator with clock output capable of producing a signal with specified rise and fall times and data pattern.
2.1.2 Signal analyzer with external clock input capable of infinite persistence display. This is typically a digital sampling oscilloscope (DSO) with sampling head. It is preferred that the DSO have masking capability. NOTE — Make sure not to exceed the maximum allowable input ratings of the oscilloscope input ports. This will prevent costly damage and provide reliable measurements. Even signal excursions that are within the maximum allowable signal levels of the oscilloscope can result in unstable eye pattern responses.
2.2 Fixture
2.2.1 The test fixtures shall provide for proper signal(s) and ground pattern(s) and, if required, proper termination of adjacent signal lines.
2.2.2 When measuring a differential response, make sure that the test fixtures and test cables are delay matched to minimize the skew. It is recommended that the skew of the test cables and fixtures be < 5% of the bit period. 3 Test specimen 3.1 Description For this test procedure the test specimen shall be as follows: 3.1.1 Separable connectors A mated connector pair. 3.1.2 Cable assembly Assembled connectors and cables, and mated connectors.

                                           Related Information                                             Download
PS:Thank you for your support!
ANSI AWS A5.03-1999(R2007) pdf download ANSI Standards

ANSI AWS A5.03-1999(R2007) pdf download

All standards (codes, specifications, recommended practices, methods, classifications, and guides) of the American Welding Society (AWS) are voluntary consensus standards that have been developed in accordance with the rules of the American National Standards Institute (ANSI). When...
Read More
ANSI AWS A5.20-1995 pdf download ANSI Standards

ANSI AWS A5.20-1995 pdf download

Note: The primary purpose of AWS is to serve and benefit its members. To this end, AWS provides a forum for the exchange, consideration, and discussion of ideas and proposals that are relevant to the welding industry...
Read More

LEAVE A REPLY

Anonymous netizen Fill in information